Friday, 2 January 2015

Production Schedule

Here is a short run through of the dates for when each stage must be completed. This is the same for all the media students. The only day that I have added is the day that I plan to shoot the entire title sequence. This could be tricky however it must be done as getting my actors to the location is very hard. Also, it needs to be at the weekend due to the fact that the days get dark very quickly and I need it to be bright and morning. This makes it hard if I forget to shoot one shot or if one shot does not look very good. To prevent this from happening I will use a shot log to make sure I shoot all the right things. I will also film each shot at least 3 times so that I have a range of shots to choose from. This was something that I did not do in my previous project which left me with 'gnarly' shots that didn't quite look right.

By 5th January - All planning complete including call sheets, storyboards and scenario
6th - 31st January  - All shooting complete and uploaded onto the media server ready for editing.
17th January-Shooting Day
3rd - 14th Febuary - First draft edit complete and uploaded onto vimeo for teacher/peer feedback.
15th Feb - 7th March - Final cut complete, feedback logged and reviewed.



No comments:

Post a Comment